Cornell Chronicle index page Table of Contents Front page of this issue

Duffield Hall takes shape: a periodic update

What: Cornell's nanotechnology research and teaching facility

Where: Engineering Quad

Cost: $58.5 million

Completion: Summer 2004

Number of floors: 3

Area: 150,930 square feet

With the completion of the first-floor elevated deck on March 21 came the emergence of 57 columns that will support the building's three floors and roof. Also completed is the backfill ­ gravel surrounding the finished walls ­ on the southern side of the building. Just about complete is the forming system ­ metal frames supporting aluminum beams and topped with a plywood deck ­ that will support half of the concrete for the building's second-floor slab.

The slab is the first-floor elevated deck that covers the basement. The 30-inch deck was poured in two sections on March 16 and 21.

This area, called slab-on-grade, is where the support of the first-floor concrete slab comes from the compacted earth, instead of from walls and columns. Last week, workers finished burying mechanical pipes and completed pouring the six-inch concrete slab. This will allow for the forming of the level-two elevated deck continuing to the southern end of the new Duffield Hall.

The building is supported on the slab-on-grade end by reinforced-concrete columns that stand on caissons (holes drilled 14 feet into the bedrock and filled with concrete). Columns supporting the building on the northern half ­ the section with a basement ­ stand directly on the bedrock one story below.

An aerial view of the construction site, taken April 7.
Jon Reis Photography/Photolink

April 18, 2002

| Cornell Chronicle Front Page | | Table of Contents | | Cornell News Service Home Page |